Porcino
For George Westen Foods
Design of project, from start to finish
Kiosk installtion
Consumer mains and site MSB housed within custom-built containerised switch room
880kVA stand by back up generator
Submains for 4 site distribution boards and associated undergrounds
Submains for 26 sheds and associated undergrounds
Custom design and built distribution / control panels for 22 finisher sheds
Electrical fit out to 22 finisher sheds, including :
Timer-controlled lighting
Auger-driven feed system
Translucent curtain droppers and winches
Ventilation fans
Misting system
Temperature, humidity and pressure sensors, to control environment within sheds
Basic electrical fit out to 4 sorting sheds and 2 control centres
Electrical fit out to amenities / office building
Electrical fit out to maintenance and storage sheds
Telemetry controlled bore water system